MWP - Features - Track progress : fix dates

MWP - Features - Track progress : fix dates

Use case

Fixing tasks dates in Microsoft Project can be challenging. Especially when you have constraint and do not want MS Project to others value.
We made an easy to use function to handle all the hassles for you.

How to

  1. Select task(s),
  2. Go to Track Progress tab,
  3. Click on Checkmark menu.
  4. Select Fix dates button,
  5. Fill the dates.

Then you only have to fill Start and Finish dates:


This feature have two constraints: 
  1. Dates must be in the past.
  2. Start is before finish.